18 CFR 4.40
§ 4.40 Applicability.
United States · 18 CFR — Conservation of Power and Water Resources · Status: effective
Cite this
- Citation
- 18 CFR 4.40, § 4.40 Applicability, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/70486
- Permanent ID
ys:prov:70486@1- SHA-256
f7464bef78b1fbd94dc1d781b8f849f6b04b3edace1fd63e1d5235fc6b84283a
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Applicability. The provisions of this subpart apply to any application for an initial license for a major unconstructed project that would have a total installed capacity of more than 10 megawatts, and any application for an initial or new license for a major modified project with a total installed capacity more than 10 megawatts. An applicant for license for any major unconstructed or major modified water power project that would have a total installed generating capacity of 10 megawatts or less must submit application under subpart G of this part (§§ 4.60 and 4.61).
(b) Guidance from Commission staff. A prospective applicant for a license for a major unconstructed project or major modified project may seek advice from the Commission's Office of Energy Projects regarding the applicability of this subpart to its project [see § 4.32(h)], including the determinations whether any proposed repair, modification or reconstruction of an existing dam would result in a significant change in the normal maximum surface elevation of an existing impoundment, or whether any proposed change in existing project works or operation would result in a significant environmental impact.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.