yourstate.us
18 CFR 4.108

§ 4.108 Contents of application for exemption from provisions other than licensing.

United States · 18 CFR — Conservation of Power and Water Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
18 CFR 4.108, § 4.108 Contents of application for exemption from provisions other than licensing, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/70519
Permanent ID
ys:prov:70519@1
SHA-256
fece8b1dac4d1c5235cf2047c84fd319583acef5ef0fddd28cefbd128e2a183e

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

An application for exemption of a small hydroelectric power project from provisions of Part I of the Act other than the licensing requirement need not be prepared according to any specific format, but must be included as an identified appendix to the related application for license or amendment of license. The application for exemption must list all sections or subsections of Part I of the Act for which exemption is requested.

Legislative history