§ 7.3 Adequacy review of application.
United States · 18 CFR — Conservation of Power and Water Resources · Status: effective
Cite this
- Citation
- 18 CFR 7.3, § 7.3 Adequacy review of application, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/70575
- Permanent ID
ys:prov:70575@1- SHA-256
9b21be8093fca2cb9df99e4291964fc97ddf85a1eba0c4c872f538aff7f16bc5
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Adequacy review of license applications. Review of the original license application for which expedited processing under this part is requested will be conducted pursuant to 18 CFR part 4 or 5, as applicable.
(b) Deficient license applications. If an original license application for which expedited processing is requested under this part is rejected under 18 CFR parts 4 and 5, as applicable, the request for authorization for the expedited licensing process under this part is deemed rejected.