§ 7.6 Notice of acceptance and ready for environmental analysis.
United States · 18 CFR — Conservation of Power and Water Resources · Status: effective
Cite this
- Citation
- 18 CFR 7.6, § 7.6 Notice of acceptance and ready for environmental analysis, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/70578
- Permanent ID
ys:prov:70578@1- SHA-256
e9d5c67f3246eb56d2e033a567ba3f1409a96d181d37cf12e1c1849bb1f8ed93
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
If the Director deems the application complete and approves the request to use the expedited licensing process under § 7.5, the Commission will issue a public notice as required in the Federal Power Act, no later than 180 days after application filing, that:
(a) Accepts the application for filing and specifies the date upon which the application was accepted for filing;
(b) Finds the application ready for environmental analysis;
(c) Requests comments, protests, and interventions;
(d) Requests recommendations, preliminary terms and conditions, and preliminary fishway prescriptions, including all supporting documentation; and
(e) Establishes an expedited licensing process schedule, including estimated dates for:
(1) Filing of recommendations, preliminary terms and conditions, and fishway prescriptions;
(2) Issuance of a draft National Environmental Policy Act (NEPA) document, or an environmental assessment not preceded by a draft;
(3) Filing of a response, as applicable, to Commission staff's request for ESA concurrence or request for formal consultation under the ESA, or responding to other Commission staff requests to federal and state agencies, or Indian Tribes pursuant to Federal law, including the Magnuson-Stevens Fishery Conservation and Management Act and the National Historic Preservation Act;
(4) Filing of comments on the draft NEPA document, as applicable;
(5) Filing of modified recommendations, mandatory terms and conditions, and fishway prescriptions in response to a draft NEPA document or environmental assessment, if no draft NEPA document is issued; and
(6) Issuance of a final NEPA document, if any.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.