yourstate.us
18 CFR 11.14

§ 11.14 Procedures for establishing charges without an energy gains investigation.

United States · 18 CFR — Conservation of Power and Water Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
18 CFR 11.14, § 11.14 Procedures for establishing charges without an energy gains investigation, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/70606
Permanent ID
ys:prov:70606@1
SHA-256
e1e7057cf4144e487cc329ad3391ff91f711912f700fda9fd98c3a7f7de08c00

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Settlements. (1) Owners of downstream and headwater projects subject to this subpart may negotiate a settlement for headwater benefits charges. Settlements must be filed with the Commission for its approval, according to the provisions of § 385.602. (2) If the headwater project is a Federal project, any settlement under this section must result in headwater benefits payments that approximate those that would result under the energy gains method. (b) Continuation of previous headwater benefits determinations. (1) For any downstream project being assessed headwater benefit charges on or before September 16, 1986, the Commission will continue to assess charges to that project on the same basis until changes occur in the river basin, including hydrology or project development, that affect headwater benefits. (2) Any procedures that apply to § 11.17(b)(5) of this subpart will apply to any prospectively fixed charges that are continued under this paragraph.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.