18 CFR 12.11
§ 12.11 Reporting modifications of the project or project works.
United States · 18 CFR — Conservation of Power and Water Resources · Status: effective
Cite this
- Citation
- 18 CFR 12.11, § 12.11 Reporting modifications of the project or project works, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/70623
- Permanent ID
ys:prov:70623@1- SHA-256
cc22a9d112ca2d57aaa2e293632c43ab5444ec6bfdb8c2060ccae1ec2b3454a5
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Reporting requirement. Regardless of whether a particular modification is permitted without specific prior Commission approval, an applicant or licensee must report any modification of the project or project works to the Regional Engineer in writing, verified in accordance with § 12.13, at the time specified in paragraph (b) of this section.
(b) Time of reporting.
(1) Any modification that is an emergency measure taken in response to a condition affecting the safety of the project or project works must be submitted with the report of that condition required by § 12.10(a)(2).
(2) In all other instances, the modification must be reported at least 60 days before work on the modification begins.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.