18 CFR 16.22
§ 16.22 Application for an exemption by a licensee with a minor or minor part license for a project not subject to sections 14 and 15 of the Federal Power Act.
United States · 18 CFR — Conservation of Power and Water Resources · Status: effective
Cite this
- Citation
- 18 CFR 16.22, § 16.22 Application for an exemption by a licensee with a minor or minor part license for a project not subject to sections 14 and 15 of the Federal Power Act, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/70688
- Permanent ID
ys:prov:70688@1- SHA-256
788a75474a58361977010979a1206ead7cca93091a74217611e842a36c12bde9
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Applicability. This section applies to an existing licensee with a license for a project not subject to sections 14 and 15 of the Federal Power Act.
(b) Information requirements. An applicant for an exemption must meet the requirements of, and will be processed in accordance with, subpart K or subpart J of part 4 of this chapter, and §§ 16.5, 16.8, 16.9(b)(2) (except the requirement to comply with §§ 4.41, 4.51, or 4.61 of this chapter), §§ 16.9(b)(3), 16.9(b)(4), 16.9(c), and 16.9(d).
(c) Standard of comparison. If an application for subsequent license is filed in competition with an application for exemption by an existing licensee, the Commission will decide among competing applications in accordance with the standards of § 16.13 and not in accordance with the provisions of § 4.37(d)(2) of this chapter.