18 CFR 35.19a
§ 35.19a Refund requirements under suspension orders.
United States · 18 CFR — Conservation of Power and Water Resources · Status: effective
Cite this
- Citation
- 18 CFR 35.19a, § 35.19a Refund requirements under suspension orders, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/70754
- Permanent ID
ys:prov:70754@1- SHA-256
0e97c47d71bc0cf77d6f04a14c46ae701b98e6b4f3f8dc43c7c87cb3c6402ff3
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Refunds.
(1) The public utility whose proposed increased rates or charges were suspended shall refund at such time in such amounts and in such manner as required by final order of the Commission the portion of any increased rates or charges found by the Commission in that suspension proceeding not to be justified, together with interest as required in paragraph (a)(2) of this section.
(2) Interest shall be computed from the date of collection until the date refunds are made as follows:
(i) At a rate of seven percent simple interest per annum on all excessive rates or charges held prior to October 10, 1974;
(ii) At a rate of nine percent simple interest per annum on all excessive rates or charges held between October 10, 1974, and September 30, 1979; and
(iii)(A) At an average prime rate for each calendar quarter on all excessive rates or charges held (including all interest applicable to such rates or charges) on or after October 1, 1979. The applicable average prime rate for each calendar quarter shall be the arithmetic mean, to the nearest one-hundredth of one percent, of the prime rate values published in the Federal Reserve Bulletin, or in the Federal Reserve's “Selected Interest Rates” (Statistical Release H. 15), for the fourth, third, and second months preceding the first month of the calendar quarter.
(B) The interest required to be paid under clause (iii)(A) shall be compounded quarterly.
(3) Any public utility required to make refunds pursuant to this section shall bear all costs of such refunding.
(b) Reports. Any public utility whose proposed increased rates or charges were suspended and have gone into effect pending final order of the Commission pursuant to section 205(e) of the Federal Power Act shall keep accurate account of all amounts received under the increased rates or charges which became effective after the suspension period, for each billing period, specifying by whom and in whose behalf such amounts are paid.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.