§ 39.2 Jurisdiction and applicability.

United States · 18 CFR — Conservation of Power and Water Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
18 CFR 39.2, § 39.2 Jurisdiction and applicability, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/70807
Permanent ID
ys:prov:70807@1
SHA-256
25784c3c2568c774c02f6e943ecda57dc99654d441e9c1beae42174989ee6419

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Within the United States (other than Alaska and Hawaii), the Electric Reliability Organization, any Regional Entities, and all users, owners and operators of the Bulk-Power System, including but not limited to entities described in section 201(f) of the Federal Power Act, shall be subject to the jurisdiction of the Commission for the purposes of approving Reliability Standards established under section 215 of the Federal Power Act and enforcing compliance with section 215 of the Federal Power Act. (b) All entities subject to the Commission's reliability jurisdiction under paragraph (a) of this section shall comply with applicable Reliability Standards, the Commission's regulations, and applicable Electric Reliability Organization and Regional Entity Rules made effective under this part. (c) Each user, owner and operator of the Bulk-Power System within the United States (other than Alaska and Hawaii) shall register with the Electric Reliability Organization and the Regional Entity for each region within which it uses, owns or operates Bulk-Power System facilities, in such manner as prescribed in the Rules of the Electric Reliability Organization and each applicable Regional Entity. (d) Each user, owner or operator of the Bulk-Power System within the United States (other than Alaska and Hawaii) shall provide the Commission, the Electric Reliability Organization and the applicable Regional Entity such information as is necessary to implement section 215 of the Federal Power Act as determined by the Commission and set out in the Rules of the Electric Reliability Organization and each applicable Regional Entity. The Electric Reliability Organization and each Regional Entity shall provide the Commission such information as is necessary to implement section 215 of the Federal Power Act.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.