yourstate.us
18 CFR 39.6

§ 39.6 Conflict of a Reliability Standard with a Commission Order.

United States · 18 CFR — Conservation of Power and Water Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
18 CFR 39.6, § 39.6 Conflict of a Reliability Standard with a Commission Order, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/70811
Permanent ID
ys:prov:70811@1
SHA-256
9f0b3897d80b491777382a88f85b666f648e8ccd231723d5304a1a58868c6c00

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) If a user, owner or operator of the transmission facilities of a Transmission Organization determines that a Reliability Standard may conflict with a function, rule, order, tariff, rate schedule, or agreement accepted, approved, or ordered by the Commission with respect to such Transmission Organization, the Transmission Organization shall expeditiously notify the Commission, the Electric Reliability Organization and the relevant Regional Entity of the possible conflict. (b) After notice and opportunity for hearing, within sixty (60) days of the date that a notice was filed under paragraph (a) of this section, unless the Commission orders otherwise, the Commission will issue an order determining whether a conflict exists and, if so, resolve the conflict by directing: (1) The Transmission Organization to file a modification of the conflicting function, rule, order, tariff, rate schedule, or agreement pursuant to section 206 of the Federal Power Act, as appropriate, or (2) The Electric Reliability Organization to propose a modification to the conflicting Reliability Standard pursuant to § 39.5 of the Commission's regulations. (c) The Transmission Organization shall continue to comply with the function, rule, order, tariff, rate schedule, or agreement accepted, approved, or ordered by the Commission until the Commission finds that a conflict exists, the Commission orders a change to such provision pursuant to section 206 of the Federal Power Act, and the ordered change becomes effective.