18 CFR 50.3
§ 50.3 Applications/pre-filing; rules and format.
United States · 18 CFR — Conservation of Power and Water Resources · Status: effective
Cite this
- Citation
- 18 CFR 50.3, § 50.3 Applications/pre-filing; rules and format, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/70857
- Permanent ID
ys:prov:70857@1- SHA-256
dbc9a55a5f0df9b522acf58cacb98e856ecf5ace127cd9580d58b3b50d0472a9
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Filings are subject to the formal paper and electronic filing requirements for proceedings before the Commission as provided in part 385 of this chapter.
(b) Applications, amendments, and all exhibits and other submissions required to be furnished by an applicant to the Commission under this part must be submitted in electronic format.
(c) When an application considered alone is incomplete and depends vitally upon information in another application, it will not be accepted for filing until the supporting application has been filed. When applications are interdependent, they must be filed concurrently.
(d) All filings must be signed in compliance with § 385.2005 of this chapter.
(e) The Commission will conduct a paper hearing on applications for permits for electric transmission facilities.
(f) Permitting entities will be subject to the filing requirements of this section and the prompt and binding intermediate milestones and ultimate deadlines established in the notice issued under § 50.9.
(g) Any person submitting documents containing critical energy infrastructure information must follow the procedures specified in § 388.113 of this chapter.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.