18 CFR 153.23
§ 153.23 Reporting requirements.
United States · 18 CFR — Conservation of Power and Water Resources · Status: effective
Cite this
- Citation
- 18 CFR 153.23, § 153.23 Reporting requirements, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/70927
- Permanent ID
ys:prov:70927@1- SHA-256
a5d9922a0c73dbdeb89acd53db19070c31e53bb963ab8836e900984d5c6895c8
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
Each person authorized under this part 153 that is not otherwise required to file information concerning the start of construction or modification of import/export facilities, the completion of construction or modification, and the commencement of service must file such information with the Commission within 10 days after such event. Each person, other than entities without pipeline capacity, must also report by March 1 of each year the estimated peak day capacity and actual peak day usage of its import/export facilities.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.