18 CFR 157.22
§ 157.22 Schedule for final decisions on a request for a Federal authorization.
United States · 18 CFR — Conservation of Power and Water Resources · Status: effective
Cite this
- Citation
- 18 CFR 157.22, § 157.22 Schedule for final decisions on a request for a Federal authorization, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/71022
- Permanent ID
ys:prov:71022@1- SHA-256
34ee905bee64c1a9eb004ac6a464ba12266c7ef1c2b0365e92469006f06531fc
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) For an application under section 3 or 7 of the Natural Gas Act that requires a Federal authorization—i.e., a permit, special use authorization, certification, opinion, or other approval—from a Federal agency or officer, or State agency or officer acting pursuant to delegated Federal authority, a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law.
(b) For requests for a water quality certification submitted pursuant to section 401(a)(1) of the Federal Water Pollution Control Act (Clean Water Act) in connection with a project for which authorization is sought from the Commission under section 3 or 7 of the Natural Gas Act, the reasonable period of time during which the certifying agency may act on the water quality certification request is one year from the certifying agency's receipt of the request. A certifying agency is deemed to have waived the certification requirements of section 401(a)(1) of the Clean Water Act if the certifying agency has not denied or granted certification by one year after the date the certifying agency received a written request for certification.