18 CFR 157.33

§ 157.33 Requirement for open season.

United States · 18 CFR — Conservation of Power and Water Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
18 CFR 157.33, § 157.33 Requirement for open season, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/71027
Permanent ID
ys:prov:71027@1
SHA-256
de77d6a16bf2072c069b670e49bd14f80c7e81b97623dc00bb6ef1202c73f308

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Any application for a certificate of public convenience and necessity or other authorization for a proposed Alaska natural gas transportation project must include a demonstration that the applicant has conducted an open season for capacity on its proposed project, in accordance with the requirements of this subpart. Failure to provide the requisite demonstration will result in an application being rejected as incomplete. (b) Initial capacity on a proposed Alaska natural gas transportation project may be acquired prior to an open season through pre-subscription agreements, provided that in any open season as required in paragraph (a) of this section, capacity is offered to all prospective bidders at the same rates and on the same terms and conditions as contained in the pre-subscription agreements. All pre-subscription agreements shall be made public by posting on Internet websites and press releases within ten days of their execution. In the event there is more than one such agreement, all prospective bidders shall be allowed the option of selecting among the several agreements all of the rates, terms and conditions contained in any one such agreement.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.