18 CFR 157.209
§ 157.209 Temporary compression facilities.
United States · 18 CFR — Conservation of Power and Water Resources · Status: effective
Cite this
- Citation
- 18 CFR 157.209, § 157.209 Temporary compression facilities, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/71047
- Permanent ID
ys:prov:71047@1- SHA-256
b4bac0d8ada6c132cffd497228b83a09edd566597eb04715b837cf85f6845e2e
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Automatic authorization. If the cost does not exceed the cost limitations set forth in column 1 of table 1 to § 157.208(d), the certificate holder may install, operate and remove temporary facilities provided that the temporary compressor facilities shall not be used to increase the volume or service above that rendered by the involved existing permanent compressor unit(s).
(b) Reporting requirements. As part of the certificate holder's annual report of projects authorized under paragraph (a) of this section, the certificate holder must report the following in the manner prescribed in §§ 157.6(a) and 385.2011 of this chapter;
(1) A description of the temporary compression facility, including the size, type and number of compressor units;
(2) The location at which temporary compression was installed, operated and removed, including its location relative to existing facilities;
(3) A description of the permanent compression facility which was unavailable, and a statement explaining the reason for the temporary compression;
(4) The dates for which the temporary compression was installed, operated and removed; and
(5) If applicable, the information required in § 157.208(e)(4).
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.