yourstate.us
18 CFR 287.101

§ 287.101 Determination of powerplant design capacity.

United States · 18 CFR — Conservation of Power and Water Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
18 CFR 287.101, § 287.101 Determination of powerplant design capacity, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/71237
Permanent ID
ys:prov:71237@1
SHA-256
7cb86d41583b719bdd03d99f4c8529a9cfe41d211b88be343f4ff87568ade808

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

For the purpose of section 103 of the Powerplant and Industrial Fuel Use Act of 1978, a powerplant's design capacity shall be determined as follows: (a) Steam-electric generating unit. The design capacity of a steam-electric generating unit shall be maximum generator nameplate rating measured in kilowatts or, if the nameplate does not have a rating measured in kilowatts, the product of the generator's kilovolt-amperes nameplate rating and power factor nameplate rating. (b) Combustion turbine. The design capacity of a combustion turbine shall be its nameplate rating measured in kilowatts, adjusted for peaking service at an ambient temperature of 59 degrees Fahrenheit (15 degrees Celsius) and at the unit's site elevation. (c) Combined cycle unit. The design capacity of a combined cycle shall be the sum of its combustion turbine nameplate rating measured in kilowatts, based on baseload operation adjusted for site elevation, and the maximum generator nameplate rating measured in kilowatts of the steam turbine portion of the unit. (d) Internal combustion engine. The design capacity of an internal combustion engine shall be the generator's nameplate rating measured in kilowatts. (e) Sunsetting provisions. This section shall cease to have effect on December 5, 2026, unless the Commission determines that the cessation deadline should be extended to a date not more than 5 years in the future after offering the public an opportunity to provide input on the costs and benefits of this section and considering that input. The Commission will publish a document in the Federal Register announcing its determination and revising or removing this section accordingly.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.