18 CFR 292.203
§ 292.203 General requirements for qualification.
United States · 18 CFR — Conservation of Power and Water Resources · Status: effective
Cite this
- Citation
- 18 CFR 292.203, § 292.203 General requirements for qualification, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/71251
- Permanent ID
ys:prov:71251@1- SHA-256
1f9f14e6ab7136bd57eab904fe494102df7ec5dcad64dc638e70e31e9f940d19
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Small power production facilities. Except as provided in paragraph (c) of this section, a small power production facility is a qualifying facility if it:
(1) Meets the maximum size criteria specified in § 292.204(a);
(2) Meets the fuel use criteria specified in § 292.204(b); and
(3) Unless exempted by paragraph (d), has filed with the Commission a notice of self-certification, pursuant to § 292.207(a); or has filed with the Commission an application for Commission certification, pursuant to § 292.207(b)(1), that has been granted.
(b) Cogeneration facilities. A cogeneration facility, including any diesel and dual-fuel cogeneration facility, is a qualifying facility if it:
(1) Meets any applicable standards and criteria specified in §§ 292.205(a), (b) and (d); and
(2) Unless exempted by paragraph (d), has filed with the Commission a notice of self-certification, pursuant to § 292.207(a); or has filed with the Commission an application for Commission certification, pursuant to § 292.207(b)(1), that has been granted.
(c) Hydroelectric small power production facilities located at a new dam or diversion.
(1) A hydroelectric small power production facility that impounds or diverts the water of a natural watercourse by means of a new dam or diversion (as that term is defined in § 292.202(p)) is a qualifying facility if it meets the requirements of:
(i) Paragraph (a) of this section; and
(ii) Section 292.208.
(2) [Reserved]
(d) Exemptions and waivers from filing requirement.
(1) Any facility with a net power production capacity of 1 MW or less is exempt from the filing requirements of paragraphs (a)(3) and (b)(2) of this section.
(2) The Commission may waive the requirement of paragraphs (a)(3) and (b)(2) of this section for good cause. Any applicant seeking waiver of paragraphs (a)(3) and (b)(2) of this section must file a petition for declaratory order describing in detail the reasons waiver is being sought.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.