§ 292.209 Exceptions from requirements for hydroelectric small power production facilities located at a new dam or diversion.

United States · 18 CFR — Conservation of Power and Water Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
18 CFR 292.209, § 292.209 Exceptions from requirements for hydroelectric small power production facilities located at a new dam or diversion, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/71256
Permanent ID
ys:prov:71256@1
SHA-256
c2ccd78be78e3a58cfa6e64bb6563cd375e3627ca22a3255ec1cf55c7e973ec9

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) The requirements in §§ 292.208(b)(1) through (3) do not apply if: (1) An application for license or exemption is filed for a project located at a Government dam, as defined in section 3(10) of the Federal Power Act, at which non-Federal hydroelectric development is permissible; or (2) An application for license or exemption was filed and accepted before October 16, 1986. (b) The requirements in §§ 292.208(b) (1) and (3) do not apply if an application for license or exemption was filed before October 16, 1986, and is accepted for filing by the Commission before October 16, 1989. (c) The requirements in § 292.208(b)(3) do not apply to an applicant for license or exemption if: (1) The applicant files a petition pursuant to § 292.210; and (2) The Commission grants the petition. (d) Any application covered by paragraph (a), (b), or (c) of this section is excepted from the moratorium imposed by section 8(e) of the Electric Consumers Protection Act of 1986, Pub. L. No. 99-495.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.