yourstate.us
18 CFR 367.52

§ 367.52 Overhead construction costs.

United States · 18 CFR — Conservation of Power and Water Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
18 CFR 367.52, § 367.52 Overhead construction costs, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/71436
Permanent ID
ys:prov:71436@1
SHA-256
4704b366138c723edbc0e161ac6c145899186ba44575163b1abed52fa17ad6de

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) All overhead construction costs, such as engineering, supervision, general office salaries and expenses, construction engineering and supervision by others than the service company, law expenses, insurance, injuries and damages, relief and pensions, taxes and interest, must be charged to particular jobs or units on the basis of the amounts of the reasonably applicable overheads. (b) As far as practicable, the determination of payroll charges includible in construction overheads must be based on the related time card distributions. Where this procedure is impractical, special studies must be made periodically of the time of supervisory employees devoted to construction activities to the end that only the overhead costs that have a definite relation to construction must be capitalized. (c) The records supporting the entries for overhead construction costs must be kept so as to show the total amount of each overhead for each year, the nature and amount of each overhead expenditure charged to each construction project and to each property account, and the bases of distribution of such costs.