yourstate.us
18 CFR 806.16

§ 806.16 Completeness of application.

United States · 18 CFR — Conservation of Power and Water Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
18 CFR 806.16, § 806.16 Completeness of application, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/72297
Permanent ID
ys:prov:72297@1
SHA-256
d1a04c3e35baa4979881fc0d8b316c18221de6dacf4dc67e514119da90c73124

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) The Commission's staff shall review the application, and if necessary, request the project sponsor to provide any additional information that is deemed pertinent for proper evaluation of the project. (b) An application deemed administratively incomplete will be returned to the project sponsor, who shall have 30 days to cure the administrative deficiencies. An application deemed technically deficient may be returned to the project sponsor, who shall have a period of time prescribed by Commission staff to cure the technical deficiencies. Failure to cure either administrative or technical deficiencies within the prescribed time may result in termination of the application process and forfeiture of any fees submitted. (c) The project sponsor has a duty to provide information reasonably necessary for the Commission's review of the application. If the project sponsor fails to respond to the Commission's request for additional information, the Commission may terminate the application process, close the file and so notify the project sponsor. The project sponsor may reapply without prejudice by submitting a new application and fee.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.