18 CFR 1308.15
§ 1308.15 Finality of decisions.
United States · 18 CFR — Conservation of Power and Water Resources · Status: effective
Cite this
- Citation
- 18 CFR 1308.15, § 1308.15 Finality of decisions, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/72519
- Permanent ID
ys:prov:72519@1- SHA-256
0fcabd15535af0319dbe448ed59a4cabca9f2c138d05c52b2c03bf843060aded
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
A decision by a Contracting Officer under the disputes clause of a contract subject to this part is final and conclusive and not subject to review by any forum, tribunal, or Government agency unless an appeal or suit is timely commenced under this part or section 10(a) (2) and (3) of the Act.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.