2 CFR 200.324

§ 200.324 Contract cost and price.

United States · 2 CFR — Federal Financial Assistance · Status: effective

Get this as JSONEmbed this
Cite this
Citation
2 CFR 200.324, § 200.324 Contract cost and price, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/784
Permanent ID
ys:prov:784@1
SHA-256
7a046fcc27772043b14cb609e77ed38ddd8e4d65365d9866623dc8ebcd61c6ee

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) The recipient or subrecipient must perform a cost or price analysis for every procurement transaction, including contract modifications, in excess of the simplified acquisition threshold. The method and degree of analysis conducted depend on the facts surrounding the particular procurement transaction. For example, the recipient or subrecipient should consider potential workforce impacts in their analysis if the procurement transaction will displace public sector employees. However, as a starting point, the recipient or subrecipient must make independent estimates before receiving bids or proposals. (b) Costs or prices based on estimated costs for contracts under the Federal award are allowable only to the extent that the costs incurred or cost estimates included in negotiated prices would be allowable for the recipient or subrecipient under subpart E of this part. The recipient or subrecipient may reference its own cost principles as long as they comply with subpart E of this part. (c) The recipient or subrecipient must not use the “cost plus a percentage of cost” and “percentage of construction costs” methods of contracting.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.