Cal. Civil Code § 8414

Cal. Civil Code § 8414

California · California Civil Code · Status: effective · Effective 2011-01-01

Get this as JSONEmbed this
Cite this
Citation
Cal. Civil Code § 8414, California, version 1 as recorded 2026-07-25, yourstate.us, https://yourstate.us/provision/790031
Permanent ID
ys:prov:790031@1
SHA-256
ef8138a8a3833e6df510a9f6de84ee0ba3f7d43538b99a082a86bfb704818330

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

A claimant other than a direct contractor may not enforce a lien unless the claimant records a claim of lien within the following times: (a) After the claimant ceases to provide work. (b) Before the earlier of the following times: (1) Ninety days after completion of the work of improvement. (2) Thirty days after the owner records a notice of completion or cessation.