yourstate.us
Cal. Civil Code § 8536

Cal. Civil Code § 8536

California · California Civil Code · Status: effective · Effective 2011-01-01

Get this as JSONEmbed this
Cite this
Citation
Cal. Civil Code § 8536, California, version 1 as recorded 2026-07-25, yourstate.us, https://yourstate.us/provision/790083
Permanent ID
ys:prov:790083@1
SHA-256
d6d0ac5ba095838d4c48ba9f9ea6a85d0cf1b926e766c3fb08a831353d727f46

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Except as provided in subdivision (b), on receipt of a stop payment notice a construction lender shall withhold from the borrower or other person to whom the lender or the owner is obligated to make payments or advancement out of the construction fund sufficient funds to pay the claim stated in the notice. (b) The construction lender may, at its option, elect not to withhold funds in any of the following circumstances: (1) The stop payment notice is unbonded. (2) The stop payment notice is given by a claimant other than a direct contractor, and a payment bond is recorded before the lender is given any stop payment notice.