Cal. Civil Code § 8612
Cal. Civil Code § 8612
California · California Civil Code · Status: effective · Effective 2012-01-01
Cite this
- Citation
- Cal. Civil Code § 8612, California, version 1 as recorded 2026-07-25, yourstate.us, https://yourstate.us/provision/790104
- Permanent ID
ys:prov:790104@1- SHA-256
2c0ad77e198dd566d85aeff9db73059b6bd00e67e6a1c8f53835e2b3531e811e
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) In order to enforce a claim against a payment bond under this title, a claimant shall give the preliminary notice provided in Chapter 2 (commencing with Section 8200).
(b) If preliminary notice was not given as provided in Chapter 2 (commencing with Section 8200), a claimant may enforce a claim by giving written notice to the surety and the bond principal within 15 days after recordation of a notice of completion. If no notice of completion has been recorded, the time for giving written notice to the surety and the bond principal is extended to 75 days after completion of the work of improvement.
(c) Commencing July 1, 2012, and except as provided in subdivision (b), if the preliminary notice was required to be given by a person who has no direct contractual relationship with the contractor, and who has not given notice as provided in Chapter 2 (commencing with Section 8200), that person may enforce a claim by giving written notice to the surety and the bond principal, as provided in Section 8614, within 15 days after recordation of a notice of completion. If no notice of completion has been recorded, the time for giving written notice to the surety and the bond principal is extended to 75 days after completion of the work of improvement.
(d) Subdivision (c) shall not apply in either of the following circumstances:
(1) All progress payments, except for those disputed in good faith, have been made to a subcontractor who has a direct contractual relationship with the general contractor to whom the claimant has provided materials or services.
(2) The subcontractor who has a direct contractual relationship with the general contractor to whom the claimant has provided materials or services has been terminated from the project pursuant to the contract, and all progress payments, except those disputed in good faith, have been made as of the termination date.
(e) Pursuant to Section 8200, this section shall not apply to a laborer, as defined under Section 8024.
(f) This section shall become operative on July 1, 2012.