yourstate.us
Cal. Civil Code § 8800

Cal. Civil Code § 8800

California · California Civil Code · Status: effective · Effective 2011-01-01

Get this as JSONEmbed this
Cite this
Citation
Cal. Civil Code § 8800, California, version 1 as recorded 2026-07-25, yourstate.us, https://yourstate.us/provision/790125
Permanent ID
ys:prov:790125@1
SHA-256
389e96bbd1cd12e6331f9a5984879b6269fd6be01dbcd80794531f913685496f

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Except as otherwise agreed in writing by the owner and direct contractor, the owner shall pay the direct contractor, within 30 days after notice demanding payment pursuant to the contract is given, any progress payment due as to which there is no good faith dispute between them. The notice given shall comply with the requirements of Chapter 2 (commencing with Section 8100) of Title 1. (b) If there is a good faith dispute between the owner and direct contractor as to a progress payment due, the owner may withhold from the progress payment an amount not in excess of 150 percent of the disputed amount. (c) An owner that violates this section is liable to the direct contractor for a penalty of 2 percent per month on the amount wrongfully withheld, in place of any interest otherwise due. In an action for collection of the amount wrongfully withheld, the prevailing party is entitled to costs and a reasonable attorney’s fee. (d) This section does not supersede any requirement of Article 2 (commencing with Section 8810) relating to the withholding of a retention.