yourstate.us
Cal. Civil Code § 8838

Cal. Civil Code § 8838

California · California Civil Code · Status: effective · Effective 2011-01-01

Get this as JSONEmbed this
Cite this
Citation
Cal. Civil Code § 8838, California, version 1 as recorded 2026-07-25, yourstate.us, https://yourstate.us/provision/790141
Permanent ID
ys:prov:790141@1
SHA-256
e13d0b4353417765af68344234a6825a240e239b31fc934489a0ea2b30c5a007

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) The direct contractor or the direct contractor’s surety, or a subcontractor or a subcontractor’s surety, is not liable for delay or damage that the owner or a contractor of a subcontractor may suffer as a result of the direct contractor giving a stop work notice and subsequently stopping work for nonpayment, if the notice and posting requirements of this article are satisfied. (b) A direct contractor’s or original subcontractor’s liability to a subcontractor or material supplier after the direct contractor stops work under this article is limited to the amount the subcontractor or material supplier could otherwise recover under this title for work provided up to the date the subcontractor or material supplier ceases work, subject to the following exceptions: (1) The direct contractor’s or original subcontractor’s liability continues for work provided up to and including the 10-day notice period and not beyond. (2) This subdivision does not limit liability for custom work, including materials that have been fabricated, manufactured, or ordered to specifications that are unique to the job.