Cal. Civil Code § 9560

Cal. Civil Code § 9560

California · California Civil Code · Status: effective · Effective 2012-01-01

Get this as JSONEmbed this
Cite this
Citation
Cal. Civil Code § 9560, California, version 1 as recorded 2026-07-25, yourstate.us, https://yourstate.us/provision/790203
Permanent ID
ys:prov:790203@1
SHA-256
fdc262e26200767cfd2499cc82c5b9ba5d9b780ff4c5eb000edf074baf2f67c5

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) In order to enforce a claim against a payment bond, a claimant shall give the preliminary notice provided in Chapter 3 (commencing with Section 9300). (b) If preliminary notice was not given as provided in Chapter 3 (commencing with Section 9300), a claimant may enforce a claim by giving written notice to the surety and the bond principal within 15 days after recordation of a notice of completion. If no notice of completion has been recorded, the time for giving written notice to the surety and the bond principal is extended to 75 days after completion of the work of improvement. (c) Commencing July 1, 2012, and except as provided in subdivision (b), if the preliminary notice was required to be given by a person who has no direct contractual relationship with the contractor, and who has not given notice as provided in Chapter 3 (commencing with Section 9300), that person may enforce a claim by giving written notice to the surety and the bond principal, as provided in Section 9562, within 15 days after recordation of a notice of completion. If no notice of completion has been recorded, the time for giving written notice to the surety and the bond principal is extended to 75 days after completion of the work of improvement. (d) Subdivision (c) shall not apply in either of the following circumstances: (1) All progress payments, except for those disputed in good faith, have been made to a subcontractor who has a direct contractual relationship with the general contractor to whom the claimant has provided materials or services. (2) The subcontractor who has a direct contractual relationship with the general contractor to whom the claimant has provided materials or services has been terminated from the project pursuant to the contract, and all progress payments, except those disputed in good faith, have been made as of the termination date. (e) Pursuant to Section 9300, this section shall not apply to a laborer, as defined under Section 8024. (f) This section shall become operative on July 1, 2012.