Cal. Public Contract Code § 6974
Cal. Public Contract Code § 6974
California · California Public Contract Code · Status: effective · Effective 2016-01-01
Cite this
- Citation
- Cal. Public Contract Code § 6974, California, version 1 as recorded 2026-07-25, yourstate.us, https://yourstate.us/provision/896185
- Permanent ID
ys:prov:896185@1- SHA-256
7a663a9d2f00cec0583c041994e469eb04d4d4bbdd5e3eef81dc5ca34afb64a6
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Upon completion of a project using the Construction Manager/General Contractor method, the regional transportation agency shall prepare a progress report to its governing body. The progress report shall include, but not be limited to, all of the following information:
(1) A description of the project.
(2) The name of the entity that was awarded the project.
(3) The estimated and actual costs of the project.
(4) The estimated and actual schedule for project completion.
(5) A description of any written protests concerning any aspect of the solicitation, bid, proposal, or award of the project, including, but not limited to, the resolution of the protests.
(6) An assessment of the prequalification process and criteria required by this chapter.
(7) A description of the method used to evaluate the bid or proposal, including the weighting of each factor and an assessment of the impact of this requirement on a project.
(8) A description of any challenges or unexpected problems that arose during the construction of the project and a description of the solutions that were considered and ultimately implemented to address those challenges and problems.
(9) Recommendations to improve the Construction Manager/General Contractor method authorized by this chapter.
(b) The progress report shall be made available on the regional transportation agency’s Internet Web site.