yourstate.us
Cal. Public Contract Code § 10262

Cal. Public Contract Code § 10262

California · California Public Contract Code · Status: effective · Effective 2012-01-01

Get this as JSONEmbed this
Cite this
Citation
Cal. Public Contract Code § 10262, California, version 1 as recorded 2026-07-25, yourstate.us, https://yourstate.us/provision/896402
Permanent ID
ys:prov:896402@1
SHA-256
1c7eece345fabf4aa61db758fa4dcb3037dd7edc7c365bc294adfb21a2b2ea52

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

The contractor shall pay to his or her subcontractors, within seven days of receipt of each progress payment, the respective amounts allowed the contractor on account of the work performed by his or her subcontractors, to the extent of each subcontractor’s interest therein. The payments to subcontractors shall be based on estimates made pursuant to Section 10261. Any diversion by the contractor of payments received for prosecution of a contract, or failure to reasonably account for the application or use of the payments constitutes ground for actions prescribed in Section 10253, in addition to disciplinary action by the Contractors’ State License Board. The subcontractor shall notify, in writing, the Contractors’ State License Board and the department of any payment less than the amount or percentage approved for the class or item of work as set forth in Section 10261.