Cal. Public Contract Code § 22192
Cal. Public Contract Code § 22192
California · California Public Contract Code · Status: effective · Effective 2025-01-01
Cite this
- Citation
- Cal. Public Contract Code § 22192, California, version 1 as recorded 2026-07-25, yourstate.us, https://yourstate.us/provision/897936
- Permanent ID
ys:prov:897936@1- SHA-256
a2e885d38c31d9142367ad8ef2e11ad184ba10f0fdb4c7f43b859d9e3f9d5215
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) (1) Upon agreement of the pricing, including any guaranteed maximum price if applicable, for any relevant aspects of the project, the city, in its sole and absolute discretion, may do all of the following:
(A) Amend its contract with the business entity.
(B) Direct the business entity to complete the remaining design, preconstruction, and construction activities sufficient to complete and close out the project or any part of the project.
(C) Add funds to the contract for the activities pursuant to this subdivision.
(2) Any amendment of the existing contract with the business entity shall not require any additional competitive process.
(3) This section does not require the city to amend an existing contract or enter into a new contract for remaining design, preconstruction, or construction activities for the project.
(b) (1) If the city and the business entity do not reach an agreement on pricing for any relevant aspect of the project, or if the city otherwise elects not to have the business entity complete some or all of the remaining work, the city may solicit proposals to complete some or all of the remaining work for the project from firms that previously submitted proposals.
(2) (A) The city may, upon written determination that it is in the best interest of the city to do so, formally solicit proposals from other business entities to complete some or all of the remaining work for the project, or complete the project using other delivery methods.
(B) If otherwise applicable to the city, any contract awarded for the project shall be made on a best value basis.