Cal. Public Resources Code § 3744

Cal. Public Resources Code § 3744

California · California Public Resources Code · Status: effective · Effective 2011-01-01

Get this as JSONEmbed this
Cite this
Citation
Cal. Public Resources Code § 3744, California, version 1 as recorded 2026-07-25, yourstate.us, https://yourstate.us/provision/898798
Permanent ID
ys:prov:898798@1
SHA-256
2a42317d5c7fb1499ae6e570b7c80a9749d187b858be4339c2ce28bc74122770

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Within 30 days from the date of service of an order made pursuant to Section 3743, or if there has been an appeal from the order to the director, within 30 days after service of the decision of the director, or if a review has been taken of the order of the director, within 10 days after the affirmance of the order, the operator shall commence in good faith the work ordered and continue it until completion. If the work has not been commenced and continued to completion, the supervisor may appoint necessary agents to enter the premises and perform the work. An accurate account of the expenditures shall be kept. Any amount so expended constitutes a lien against the real or personal property of the operator upon which the work is done and the lien has the force, effect, and priority of a judgment lien pursuant to Section 3772. (b) Notwithstanding Section 3741, 3743, or 3755, if the supervisor determines that an emergency exists, the supervisor may make formal or emergency orders or undertake any other action that the supervisor determines to be necessary for the protection of life, health, property, or natural resources.