Cal. Public Utilities Code § 1003
Cal. Public Utilities Code § 1003
California · California Public Utilities Code · Status: effective
Cite this
- Citation
- Cal. Public Utilities Code § 1003, California, version 1 as recorded 2026-07-25, yourstate.us, https://yourstate.us/provision/908415
- Permanent ID
ys:prov:908415@1- SHA-256
1586ebf4c04353db0d4cbb5a49b1e0d07034b3bfb05db8db26ba5e41825e1dc9
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
Every electrical and every gas corporation submitting an application to the commission for a certificate authorizing the new construction of any electric plant, line, or extension, or gas plant, line, or extension, not subject to the provisions of Chapter 6 (commencing with Section 25500) of Division 15 of the Public Resources Code, shall include all of the following information in the application in addition to any other required information:
(a) Preliminary engineering and design information on the project. The design information provided for thermal electric plants shall include preliminary data regarding the operating characteristics of the proposed plant, including, but not limited to, the annual capacity factor, availability factor, and the heat rate for each year of the useful life of the plant, line, or extension.
(b) A project implementation plan showing how the project would be contracted for and constructed. This plan shall show how all major tasks would be integrated and shall include a timetable identifying the design, construction, completion, and operation dates for each major component of the plant, line, or extension.
(c) An appropriate cost estimate, including preliminary estimates of the costs of financing, construction, and operation, including fuel, maintenance, and dismantling or inactivation after the useful life of the plant, line, or extension.
(d) A cost analysis comparing the project with any feasible alternative sources of power. The corporation shall demonstrate the financial impact of the plant, line, or extension construction on the corporation’s ratepayers, stockholders, and on the cost of the corporation’s borrowed capital. The cost analyses shall be performed for the projected useful life of the plant, line, or extension, including dismantling or inactivation after the useful life of the plant, line, or extension.
(e) A design and construction management and cost control plan which indicates the contractual and working responsibilities and interrelationships between the corporation’s management and other major parties involved in the project. This plan shall also include a construction progress information system and specific cost controls.