§ 140.609 Progress and final vouchers.
United States · 23 CFR — Highways · Status: effective
Cite this
- Citation
- 23 CFR 140.609, § 140.609 Progress and final vouchers, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/96477
- Permanent ID
ys:prov:96477@1- SHA-256
f9fd4f8b5631040ab3fff15be39008be2d44cca9b6828161a55a657e52671cc5
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Progress vouchers may be submitted for the Federal share of bonds retired or about to be retired, including eligible interest on Interstate Bond Issue Projects, the proceeds of which have actually been expended for the construction of the project.
(b) Upon completion of a bond issue project, a final voucher shall be submitted by the SHA. After final review, the SHA will be advised as to the total cost and Federal fund participation for the project.