23 CFR 635.121
§ 635.121 Contract time and contract time extensions.
United States · 23 CFR — Highways · Status: effective
Cite this
- Citation
- 23 CFR 635.121, § 635.121 Contract time and contract time extensions, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/96866
- Permanent ID
ys:prov:96866@1- SHA-256
3ad724e6dd5e0d4460efe9f668e39979fa6223174454ae03fa52f1112f09bf4c
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) The State DOT should have adequate written procedures for the determination of contract time. These procedures should be submitted for approval to the Division Administrator within 6 months of the effective date of this Final Rule.
(b) Contract time extensions granted by a State DOT shall be subject to the concurrence of the Division Administrator and will be considered in determining the amount of Federal participation. Contract time extensions submitted for approval to the Division Administrator, shall be fully justified and adequately documented.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.