23 CFR 635.307
§ 635.307 Coordination.
United States · 23 CFR — Highways · Status: effective
Cite this
- Citation
- 23 CFR 635.307, § 635.307 Coordination, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/96883
- Permanent ID
ys:prov:96883@1- SHA-256
ddc889f8e990e7699c3851172d4859b8da6cce82ebb3cc513a34c13b0db8a790
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) The right-of-way clearance, utility, and railroad work are to be so coordinated with the physical construction that no unnecessary delay or cost for the physical construction will occur.
(b) All right-of-way clearance, utility, and railroad work performed separately from the contract for the physical construction of the project are to be accomplished in accordance with provisions of the following:
(1) 23 CFR part 140, subpart I;
(2) 23 CFR part 646, subpart B;
(3) 23 CFR 710.403; and
(4) 23 CFR part 645, subpart A.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.