§ 636.208 May I use my existing prequalification procedures with design-build contracts?

United States · 23 CFR — Highways · Status: effective

Get this as JSONEmbed this
Cite this
Citation
23 CFR 636.208, § 636.208 May I use my existing prequalification procedures with design-build contracts?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/96939
Permanent ID
ys:prov:96939@1
SHA-256
39b681aa9369d98257646577a1eba2da226bf376c944465a31bf5b930b3e7f18

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

Yes, you may use your existing prequalification procedures for either construction or engineering design firms as a supplement to the procedures in this part.