23 CFR 636.212
§ 636.212 To what extent must tradeoff decisions be documented?
United States · 23 CFR — Highways · Status: effective
Cite this
- Citation
- 23 CFR 636.212, § 636.212 To what extent must tradeoff decisions be documented?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/96943
- Permanent ID
ys:prov:96943@1- SHA-256
630fa6b6eff72ec5ceeebfae4fe8052d4c009468286dfc94f0bcb389774f233a
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
When tradeoffs are performed, the source selection records must include the following:
(a) An assessment of each offeror's ability to accomplish the technical requirements; and
(b) A summary, matrix, or quantitative ranking, along with appropriate supporting narrative, of each technical proposal using the evaluation factors.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.