yourstate.us
23 CFR 650.209

§ 650.209 Construction.

United States · 23 CFR — Highways · Status: effective

Get this as JSONEmbed this
Cite this
Citation
23 CFR 650.209, § 650.209 Construction, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/97048
Permanent ID
ys:prov:97048@1
SHA-256
0dfe8d02d58c8a4c7780d33afb0d82b25b3b7a7ea4c925615310d5072cba58c8

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Permanent erosion and sediment control measures and practices shall be established and implemented at the earliest practicable time consistent with good construction and management practices. (b) Implementation of temporary erosion and sediment control measures and practices shall be coordinated with permanent measures to assure economical, effective, and continuous control throughout construction. (c) Erosion and sediment control measures and practices shall be monitored and maintained or revised to insure that they are fulfilling their intended function during the construction of the project. (d) Federal-aid funds shall not be used in erosion and sediment control actions made necessary because of contractor oversight, carelessness, or failure to implement sufficient control measures. (e) Pollutants used during highway construction or operation and material from sediment traps shall not be stockpiled or disposed of in a manner which makes them susceptible to being washed into any watercourse by runoff or high water. No pollutants shall be deposited or disposed of in watercourses.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.