23 CFR 655.605
§ 655.605 Project procedures.
United States · 23 CFR — Highways · Status: effective
Cite this
- Citation
- 23 CFR 655.605, § 655.605 Project procedures, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/97086
- Permanent ID
ys:prov:97086@1- SHA-256
d610893d3fb8289fff88c0ec67e3e844ef24fe57b03e86cbec88ba0acc3a6bda
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Federal-aid highways. Federal-aid projects involving the installation of traffic control devices shall follow procedures as established in 23 CFR part 630, subpart A, Federal-Aid Programs Approval and Project Authorization. Simplified and timesaving procedures are to be used to the extent permitted by existing policy.
(b) Off-system highways. Certain federally funded programs are available for installation of traffic control devices on streets and highways that are not on the Federal-aid system. The procedures used in these programs may vary from project to project but, essentially, the guidelines set forth herein should be used.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.