23 CFR 710.301

§ 710.301 General.

United States · 23 CFR — Highways · Status: effective

Get this as JSONEmbed this
Cite this
Citation
23 CFR 710.301, § 710.301 General, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/97227
Permanent ID
ys:prov:97227@1
SHA-256
e2a1b33f6b92ca33fc6c55f7306c80ed3991ad4a152e1dc85bc5db0f19b61b3d

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

The project development process typically follows a sequence of actions and approvals in order to qualify for funding. The key steps in this process typically are planning, environmental review, project agreement/authorization, acquisition, construction advertising, and construction.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.