24 CFR 35.120
§ 35.120 Options.
United States · 24 CFR — Housing and Urban Development · Status: effective
Cite this
- Citation
- 24 CFR 35.120, § 35.120 Options, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/98277
- Permanent ID
ys:prov:98277@1- SHA-256
25edcd7735d0e8f5019abfdb24c9d0865e0bdef27d03b2311ae43f9d0fbd35a0
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Standard treatments. Where interim controls are required by this part, the designated party has the option to presume that lead-based paint or lead-based paint hazards or both are present throughout the residential property. In such a case, evaluation is not required. Standard treatments shall then be conducted in accordance with § 35.1335 on all applicable surfaces, including soil. Standard treatments are completed only when clearance is achieved in accordance with § 35.1340.
(b) Abatement. Where abatement is required by this part, the designated party may presume that lead-based paint or lead-based paint hazards or both are present throughout the residential property. In such a case, evaluation is not required. Abatement shall then be conducted on all applicable surfaces, including soil, in accordance with § 35.1325, and completed when clearance is achieved in accordance with § 35.1340. This option is not available in public housing, where inspection is required.
(c) Lead hazard screen. Where a risk assessment is required, the designated party may choose first to conduct a lead hazard screen in accordance with § 35.1320(b). If the results of the lead hazard screen indicate the need for a full risk assessment (e.g., if the environmental measurements exceed levels established for lead hazard screens in § 35.1320(b)(2)), a complete risk assessment shall be conducted. Environmental samples collected for the lead hazard screen may be used in the risk assessment. If the results of the lead hazard screen do not indicate the need for a follow-up risk assessment, a risk assessment is not required.
(d) Paint testing. Where paint stabilization or interim controls of deteriorated paint surfaces are required by this rule, the designated party has the option to conduct paint testing of all surfaces with non-intact paint. If paint testing indicates the absence of lead-based paint on a specific surface, paint stabilization or interim controls are not required on that surface.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.